Search

UDRI Home


UDRI Facilities

 
Related Links

Division:
Nonmetallic Materials

Group:
Polymers, Nanocomposites and Composites

Capabilities:
E-Beam Laboratory

People:
Don Klosterman

Construction of the E-Beam Laboratory

Background: A one-year period was required to prepare the facility and fabricate, test, deliver, and install the e-beam system. The following picture-narrative chronicles the facility preparation and e-beam system installation process, which took place at the National Composite Center from October 1999 through May 2000. (Click on thumbnails to view photos.)

Step 1: It was determined that the existing floor at NCC would not support the weight of the five-foot-thick concrete walls that were designed to shield radiation in the new e-beam facility.  Steps 1-3 were taken to provide a secure foundation.  The first step involved cutting existing slab floor and excavating to a depth of one foot:

construct A2 Ebeam a1 

Step 2: Install 14 "augercast" pilings (concrete columns) to a depth of 30 feet (hitting bedrock).  This process required special equipment capable of drilling 18"-wide, 30-foot holes.  Each hole was drilled in depth increments of five feet (i.e., attach steel auger section to forklift, drill down five feet, leave auger in ground and release from forklift, raise forklift and attach new auger, drill five more feet, etc.).  Concrete was poured down the hollow shaft of the 30-foot auger assembly during its retraction.  Although the pilings will support the entire slab floor to be installed next, they are located directly underneath where the five-foot-thick concrete walls will come to bear:

construct B1 construct B2 construct B3 construct B4 construct B6

Step 3: Install rebar and cast new, one-foot-thick concrete slab:

construct C1 construct C3

Step 4: Set up forming walls and cast 71 cubic yards of concrete (seven truck-loads full!):

construct C5 construct D1 construct D2 construct D3 construct D4

Step 5: Remove forming walls: concrete walls finished!:

construct E2 construct E1 construct E3 construct E4

Step 6: Construct concrete beams that will serve as roof, paint beams and walls, and assemble crane. (The crane structure appears slanted or warped due to camera lens distortion.):

construct F2 construct F1

Step 7: Lift and position most of the ceiling blocks, leaving a hole in the top for access to the accelerator electronics during installation:

construct Block1 construct Block2 construct Block3

Step 8: Unload and unpack e-beam electronics and control systems, shipped from ESI, Inc. in Sommerville, Massachusetts:

construct Unload1 construct Unload2 construct Unload3

Step 9: Install accelerator head, run cables, and make connections:

construct Unload4 construct Wire1 construct Wire2

Step 10: Install final ceiling blocks, then begin testing e-beam gun:

construct Block4

Final Pictures: (left) Overall layout of facility, including security fence (control area is located on opposite end); (center) John Murphy and Dan Goodman during system operation, April 2000; (right) facility open house, May 2000, (from left to right): Don Klosterman (UDRI), Charles Lee (AFOSR), Janis Brown (AFRL), Richard Chartoff (UDRI).

construct Fence construct John Dan construct Group


©2008 All rights reserved. Send comments to the Webmaster.